works in progress
Originally posted 2/28
I have felt guilty for weeks with not commenting on this inspection report and the licencee not accepting the NRC's minimalist finding. They are wasting the NRC's time and their own.
Basically the industry has been recently trying to dial down the CDBI inspections in regulatory reduction. It is as wasting everyone's time.
I think the gist of this stupid is Hope Creek violation was preforming a intentional experiment on the plant. The NRC gave Hope Creek a gift...then they wouldn't accept the gift. They were having troubles with this valve for years with leaking and they didn't have a adequate safe replacement. They gambled if they turned the valve around from normal...had the flow holding the valve shut against pressure, it would fix the leak. They valve was never designed for this duty, basic engineer work...so there was much more friction opening and closing this valve.
I think this is a symtom of a attitude problem with Hope Creek, they are trying to disrupt and weaken NRC authority and oversight over frivolous non sited violation regulatory disputes. It like a cop stops you for speeding and he then lets you off with just a verbal warning.
February
9, 2016
SUBJECT:
RESPONSE TO DISPUTED NON-CITED VIOLATION HOPE CREEK GENERATING STATION –
COMPONENT DESIGN BASES INSPECTION REPORT 05000354/2015007
Dear
Mr. Davison:
We
received your response [ADAMS No. ML15362A564] to our inspection report
05000354/2015007 [ADAMS No. ML15329A157]
issued on
November 25, 2015, concerning activities conducted at your facility.
In your response, you denied a Non-Cited Violation (NCV) contained in the
inspection report. Specifically, PSEG contends that “the weaknesses identified
in the inspection report regarding classification, evaluation and corrective
actions are not more than minor in that PSEG’s conclusion on operability and
corrective actions were not impacted.”
The
NRC conducted a detailed review of your response and the applicable inspection
guidance. Region I staff who were not involved with the initial inspection
effort performed this review. After careful consideration of the bases for your
denial of the NCV, we determined that the violation and characterization of the
finding were properly described in the inspection report. Specifically, the
inspection team identified that your staff failed to conduct operability
determinations in October 2013 following the improper installation of a service
water system valve and a subsequent event where the valve failed to operate due
to a high torque condition. In response to the inspection team’s questions,
your staff, with support from an external engineering organization, performed
an operability review and determined that the valve was able to perform its
safety function for a limited number of operating cycles. You subsequently
scheduled a maintenance activity to fully restore the valve during the October
2016 refueling outage. Our review determined that this finding was
appropriately characterized as “more than minor” as there was a reasonable
basis for questioning operability of the valve following the October 2013
events described above. We have provided a summary of our evaluation and
conclusions as an enclosure to this letter.
SUMMARY
Non-Cited Violation (NCV)
05000354/2015007-02
Restatement of the Violation:
The team identified a Green NCV
of 10 CFR Part 50, Appendix B, Criterion V, “Instructions, Procedures, and
Drawings,” because PSEG did not provide adequate work order instructions for
the installation of service water (SW) pump discharge isolation valve 2198C
following planned valve maintenance in October 2013. Specifically, the
inadequate work order instructions contributed directly to maintenance
technicians installing the valve in the opposite orientation compared to the
intended orientation.
Licensee Response (Summary):
PSEG denies that the NRC
identified any new information that impacted the licensee’s conclusions
regarding operability or corrective actions. The improper re-installation of
the valve EAHV-2198C was promptly identified by the licensee and entered in
CAP, and the additional analyses performed in response to NRC questions
supported the licensee’s initial conclusions.
In addition, PSEG contends the
identified weaknesses associated with the classification, evaluation, and
corrective actions of EAHV-2198C do not meet the threshold for more than minor.
NRC Evaluation:
The NRC Region I staff performed
an independent review of the documented NCV in Inspection Report
05000354/2015007, using PSEG’s basis for denial for comparison, and made the
following observations:
1) Notification (NOTF) 20626219
was initiated by the PSEG staff on October 22, 2013, identifying the
installation of valve 2198C 180 degrees different than when removed. This NOTF
was subsequently updated by the PSEG maintenance staff to reflect inadequacies
in the applicable Work Order (60112463-410) as compared to the valve drawing
(M-10-1) and the associated vendor manual. The NCV properly refers to 10 CFR
50, Appendix B, Criterion V, as the appropriate violation of regulatory
requirements.
2) The Component Design Bases
Inspection (CDBI) report states (page 6) that “there was no documented
evaluation of the impact of this misalignment and configuration error prior to
operations declaring the C SW pump operable following the 2198C maintenance on
October 23.” As stated in the report and further clarified by interview with
the inspection team leader, PSEG did not complete an operability evaluation
prior to restoration of the C SW pump to service on October 23, 2013, in spite
of the improper installation of the outlet valve. Further, PSEG acknowledged this
deficiency by initiating NOTF 20705874 (also documented in the report). The
inspection report (page 7) identified a second instance where PSEG failed to
properly assess a valve operational anomaly, an unexpected high opening torque
(compared to the valve’s weak link analysis and Limitorque limits) and its
potential adverse impact on system operability.This condition was identified
during troubleshooting of valve 2198C on October 27, 2013, but no corresponding
operability evaluation was documented.
3) The team’s observations
documented in the report and highlighted in 2) above, form the basis for the
inspection team’s conclusion that the NRC added value to a licensee-identified
finding or violation. The absence of an operability evaluation, for either of
the above referenced conditions, was documented as a “weakness in the
licensee’s classification, evaluation, or corrective action” (page 9) and was
the basis for the team to conclude there was a reasonable doubt of operability,
with respect to the valve being able to function under all design basis
conditions. In order to conclude that the valve was operable and to answer
questions from the inspection team, PSEG performed an operability determination
for the issue of the valve being installed in the wrong orientation (NOTF
20705874), performed a technical evaluation to determine that the valve
actuator was capable of opening the valve under all required design basis
conditions based upon actual measured data (NOTF 20704783), and contracted with
Kalsi Engineering to perform an H4BC gear box torque analysis for the valve
actuator. This team conclusion was documented in the Analysis Section of the
inspection report (page 9-10) in reference to the basis for the observations
(and underlying performance deficiency) being more than minor. The team cites
Example 3.j of IMC 0612, Appendix E, as justification of the more than minor
determination.
4) PSEG’s Basis for Denial did
not address the Appendix E more than minor example referenced in the CDBI
inspection report. Rather, PSEG stated that the weaknesses identified by the
team regarding classification, evaluation and corrective action were not more
than minor. Further, PSEG contends that the additional analyses performed in
response to NRC team questions did not change the original operability
determination outcome. Neither the subjective contention of the weaknesses
being minor nor the final determination of operability being maintained provide
a sufficient basis for denial. The NRC determined that the Appendix E example
established the basis for determining that this performance deficiency was of more
than minor significance.
5) In the Basis for Denial, PSEG
opines that the CDBI team’s challenge of the operability impact of the above
conditions was unfounded without knowledge of the actual operating conditions
of the system (system alignment, flowrates, and valve differential pressure
were not recorded and were unknown). PSEG contends that without knowing actual
system operating conditions, data cannot be extrapolated with any certainty.
The NRC considers that the uncertainties associated with the valve operating
parameters highlight the reason why PSEG was required to perform an operability
determination following improper installation of the valve and its failure to
operate due to a high torque condition.
6) Additionally, PSEG took
exception to the observation in the inspection report that the maintenance work
instructions lacked sufficient detail. On page 6 of the inspection report, the
inspection team noted that PSEG maintenance personnel identified and documented
in NOTF 20626219, that the desired orientation of the 2198 valve was not
specified in valve drawing M-10-1 or in the vendor manual. The inspection team
also noted that the work order contained several diagrams which depicted the
wrong valve orientation. The NRC determined that the maintenance work
instructions given to the maintenance staff lacked sufficient detail to ensure
that the valve was installed in the proper orientation.
For the above reasons, the staff
concludes that the violation occurred as described in Inspection Report 05000354/2015007.