You notice it does specify when this event began. I hope they kicked the offending executive off the site. This is a falsification of a document, but the NRC never takes falsification seriously.  

Power Reactor Event Number: 53830
Facility: FERMI
Region: 3     State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: JEFF MEYERS
HQ OPS Officer: THOMAS KENDZIA
Notification Date: 01/16/2019
Notification Time: 18:38 [ET]
Event Date: 01/16/2019
Event Time: 00:00 [EST]
Last Update Date: 01/16/2019
Emergency Class: NON EMERGENCY
10 CFR Section:
26.719 - FITNESS FOR DUTY

Person (Organization):
PATRICIA PELKE (R3DO)
FFD GROUP (EMAIL)
WILLIAM GOTT (IRD)
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
SIGNIFICANT FITNESS-FOR-DUTY POLICY VIOLATION

"At 0900 EST on 01/16/2019, it was discovered that a licensee manager intentionally failed to re-approve the list of individuals granted unescorted access to verify each individual was subject to a behavioral observation program. Compensatory actions have been taken in response to this event. Personnel affected have had their access authorization suspended.

"This is reportable under the provisions of 10 CFR 26.719(b)(3) as an intentional act that casts doubt on the integrity of the Fitness-For-Duty program.

"The licensee notified the NRC Resident Inspector."