Thursday, March 23, 2017

New Junk Plant Watts Bar 2 is a Lemon

So two scrams in three days. These guys got serious safety cultures problems and a very poor initial startup record...

Heading for a 95001?

Power Reactor
Event Number: 52630
Facility: WATTS BAR
Region: 2 State: TN
Unit: [ ] [2] [ ]
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: DAMON FEGLEY
HQ OPS Officer: KARL DIEDERICH
Notification Date: 03/23/2017
Notification Time: 02:48 [ET]
Event Date: 03/23/2017
Event Time: 00:14 [EDT]
Last Update Date: 03/23/2017
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
Person (Organization):
MIKE ERNSTES (R2DO)

Unit
SCRAM Code
RX CRIT
Initial PWR
Initial RX Mode
Current PWR
Current RX Mode
2
N
Y
16
Power Operation
3
Startup
Event Text
AUTOMATIC START OF AUXILIARY FEED WATER

"On March 23, 2017, at 0014 EDT, Watts Bar Nuclear Plant Unit 2 (WBN2) experienced an unplanned trip of both Turbine Driven Main Feed Pumps (TDMFP) following a loss of Main Condenser Vacuum. The trip of both TDMFPs caused an automatic start of both Motor Driven Auxiliary Feed Water Pumps and the Turbine Driven Auxiliary Feed Water Pump. [The] cause of the loss of Main Condenser Vacuum is currently under investigation."

The plant was performing a normal startup, and had just synced the main generator to the grid. Subsequent to the event, the plant was transitioned to Mode 3 by inserting all rods with a manual trip. Decay heat is being removed via the atmospheric relief valves.

Unit 1 remains in Mode 5 for a refueling outage.

The licensee has notified the NRC Resident Inspector.


Power Reactor
Event Number: 52625
Facility: WATTS BAR
Region: 2 State: TN
Unit: [ ] [2] [ ]
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: JOHN TUITE
HQ OPS Officer: NESTOR MAKRIS
Notification Date: 03/20/2017
Notification Time: 10:17 [ET]
Event Date: 03/20/2017 Event Time: 08:13 [EDT]
Last Update Date: 03/20/2017
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
Person (Organization):
MIKE ERNSTES (R2DO)

Unit
SCRAM Code
RX CRIT
Initial PWR
Initial RX Mode
Current PWR
Current RX Mode
2
M/R
Y
91
Power Operation
0
Hot Standby
Event Text
MANUAL REACTOR TRIP AS A RESULT OF SECONDARY PLANT TRANSIENT

"On March 20, 2017 at 0813 EDT, Watts Bar Nuclear Plant (WBN) Unit 2 operations personnel manually tripped the plant from approximately 91 percent power based on lowering steam generator levels. Prior to the plant trip, the 2A Hotwell pump tripped at 0758 EDT and the 2C Condensate Booster Pump subsequently tripped at 0802 EDT. Operations personnel commenced to lower plant power after the 2A Hotwell pump trip in an attempt to maintain steam generator levels, but were unable to recover level and manually tripped the unit.

"All control rods fully inserted and all automatically actuated safety related equipment operated as designed. At 0905 EDT, operations personnel exited the emergency operating instructions after the plant was stabilized. The cause of the event is under investigation.

"This event is reportable to the NRC within four hours under 10 CFR 50.72(b)(2)(iv)(B) as a result of the actuation of the Reactor Protection System and in eight hours under 10 CFR 50.72(b)(3)(iv)(A) as a result of actuation of the Auxiliary Feedwater system.

"The licensee notified the NRC Resident Inspector."

No comments:

Post a Comment