Sunday, January 11, 2015

Millstone's and the NRC's management has been Negligent!

The NRC has a habit of disclosing troubling information about a plant, sometimes many years after the event...they wait until the crisis is over and well settled. I think this basically is the agency's strategy of sugar coating event... basically giving us false and incomplete information when the situation is on going to protect the plant. Then dishing out the bad news months after the crisis is complete. The agency knows that the bad news more sticks to a bad actor with a on going crisis than it released months after the situation.
The inspection staff is nothing but whore for Dominion.
"(Jan 11) And Raymond McKinley, an NRC official who oversees inspectors at Millstone and two other plants, wrote in a December 2013 email that Millstone considered asking for a one-time change in guidelines "to buy some time" to fix a problem."
We think this more has to do with mismanagement with Region I...they don't know how to sent a strong signal to the top of the corporation demanding a immediate turnaround with a sinking ship. Pilgrim Reflects this also with their many shutdowns and we are waiting on the inspection on this. So the NRC's polities are dysfunctional with emergent on problems...The agency just doesn't have a big enough hammer to get the attention of upper management.  

It should be noted with North Anna that was extremely unprofessional...their large fuel damage accident. So if you ask me what is going on here, NRC management is Region 1 and Dominions management with nuclear is declining together. 
Millstone: UFSAR Safety Valves not fixed because of "scheduling, engineering, and funding challenges". 
My above article indicates Millstones had severely declining right under the eyes of the NRC for many years and the NRC just hasn't been enforcing their regulations and tech specs on Dominion. 

The recent switch yard LOOP and they yanking out a important protective circuit without permission and the NRC not catching them on it indicates the profound weakness of the NRC and Dominion?
Feds privately rap Millstone over response to pump problem 
By Associated Press Published: January 11, 2015, 11:37 am

HARTFORD, Conn. (AP) — As Connecticut’s nuclear plant struggled for months last year to fix a critical water pump, federal regulators expressed concern among themselves that the Millstone Power Station was slow to grasp the scope of the issue and make corrections, according to internal emails. 
The auxiliary pump, which cools the reactor in emergencies if offsite power and diesel generators fail, did not operate properly during tests in November and December 2013 and again in January 2014 before the problem was fixed. In February, the Nuclear Regulatory Commission sent a team for a closer inspection and, six months later, issued a finding of low to moderate safety problems. 
The handling of the issue also raised alarms at the local Nuclear Energy Advisory Council, which questioned Millstone officials last September about the repeated problems. 
“What concerned us the most is that it seemed out of character,” said John Sheehan, chairman of the council that oversees Connecticut nuclear power plant issues. “In previous years they were very alert to problems and correcting them. They seemed to miss this time.” 
Stephen Scace, Millstone’s site vice president, wrote to Sheehan on Nov. 10 and said there is “room to improve” how it identifies and evaluates problems. 
Ken Holt, Millstone’s spokesman, told The Associated Press the owners of the plant have revamped their approach to trouble-shooting following its work with federal regulators. 
“If it’s not immediately obvious why it’s not working, we put a team to work on it,” he said. 
Millstone, which is owned by Richmond, Virginia-based Dominion Resources Inc., operates two reactors in Waterford and generally supplies half of all power in Connecticut and 12 percent of New England’s. 
Privately, NRC inspectors voiced concern of Millstone’s handling of the problem, according to emails obtained by The Associated Press in a public records request. 
Brian Haagensen, a resident inspector at the plant, wrote to NRC colleagues on Aug. 28, 2014, that Millstone missed opportunities over several months before the problem was identified in January 2014. He said plant officials were wrong to insist that the faulty bearing was the only pump problem.
The NRC seen the developing problems for many years and they never appositely response...mainly budget and inappropriate priorities.  I mean, the inspectors and their bosses seen it coming, but I doubt higher management understood what it means. Bottom line, the agency is engineered to be reactive.  



(2013004)"The valves were initially scheduled to be restored to full qualification during refueling outage (RFO), 3RFO12, in October 2008, but the repairs were deferred to 3RFO13 due to maintenance schedule conflicts. Subsequently, repairs were not completed in 3RFO13, 3RFO14, or 3RFO15 due to scheduling, engineering, and funding challenges."
“I believe we make it clear that the incorrect bearing was only a small part of a much larger problem,” he wrote, citing Millstone’s failure to determine that an incorrect bearing had been installed sooner.
He pointed to a violation cited by the NRC that said Millstone should have identified sooner that an incorrect bearing had been installed in the pump. “While it was ultimately identified in January 2014, there were opportunities to identify it beginning in August 2013,” the inspection team wrote.
And Raymond McKinley, an NRC official who oversees inspectors at Millstone and two other plants, wrote in a December 2013 email that Millstone considered asking for a one-time change in guidelines “to buy some time” to fix a problem.
“No indication that they believe there is a problem, but I am sure they have heard enough questions and want to put the issue to bed,” he said.
Josephine Ambrosini, an NRC senior inspector, said in a May 7, 2014, email that the “earliest indications” of a problem with the pump were evident in the spring of 2013. Millstone took a long time to address the concerns, she said.
Sheehan, chairman of the local advisory council, told the AP its members were worried that problems in the 1990s when Northeast Utilities operated Millstone — such as safety issues and whistleblower complaints — were at risk of recurring. Dominion purchased Millstone in 2001.
“We were concerned it was the start of what happened in the 1990s when NU ran the plant, that their strict culture was starting to break down,” he said. “We wanted to catch it before it catches you.”

No comments: