Thursday, March 01, 2012

Byron Switchyard Insulator 2.206


So what would prevent all the defective switchyard insulators from breaking and shorting in a heavy storm, tornado or earthquake and then causing another LOOP...

The last LOOP at the plant was extraordenary, in that the plant was disconnected from grid for 31 hours. LOOPs are generially 1,2 to less than 4 hours duration.

March 20:

Exelon upgrades equipment at Byron nuclear plant

The Associated Press

BYRON, Ill. -- Exelon Energy says it has finished upgrading equipment at a northern Illinois nuclear plant where a power failure caused a reactor to shut down two months ago.
The company says it has replaced electrical insulators in the switchyards that help move power to and from the reactors at the Byron Generating Station, which is located about 95 miles northwest of Chicago.
In January, an insulator in Unit 2 switchyard failed and interrupted power, causing the reactor to automatically shut down as a precaution.
Insulators are protective equipment that helps regulate the flow of electricity. Exelon says Unit 1 was taken offline last week while upgrades were finished, and Unit 2 upgrades were finished over the weekend. Both units are back online at full power and generating electricity.

Read more here: http://www.bnd.com/2012/03/20/2107206/exelon-upgrades-equipment-at-byron.html#storylink=cpy